Stay cables reference list

Page 1 of 3  > >>

High speed train line Milan – Bologna

18 12 2006
The new railway linking Bologna to Milan is part of the High Speed Lines network at present under construction in Italy.
[...]


The "Colletta" cable stayed bridge over the Sangone creek

16 07 2005
During the October 2000 flood almost all the watercourses in the province of Turin that were tributaries of the Po river underwent exceptional high waters and consequent flooding, which caused enormous economic and environmental damage.
[...]


Arch bridge over the Twente canal

06 07 2005
The existing double railway bridge was too low and too old. The crossing with the Twente canal was too low; the bridge was technically at the end of its lifetime. A unique opportunity to design and build another railway cable-stayed bridge in the Netherlands.
[...]


Cable-stayed bridge over the River Paranaíba

04 11 2003
Although the Paranaíba Bridge was the first cable-stayed bridge to break ground in Brazil
[...]


Sea Pallini bridge, Athens

02 10 2003
The “Sea Pallini” cable stayed bridge, crossing the main highway reaching the new airport of Athens...
[...]


Dintelhaven cable-stayed bridge

published: 03 09 2000
The Holland Railways developed the "Betuwe Route" Project whose purpose was to

The Holland Railways developed the "Betuwe Route" Project whose purpose was to link Rotterdam to the Ruhr Freight Railways in Germany. The Dintelhaven bridge, which has been erected in the "Haven" zone of Rotterdam, was the first structure of this ambitious programme.

The bridge, whose total length is 280 m., has an arch shape and the stay cables hang the steel deck to the arch itself.

The stays are made of hot dip galvanised, 7 wires, 15.7 mm. diameter, high strength (1770 N/mm2), waxed, HDPE coated strands and externally protected by white HDPE sheaths.

Two planes of 15 practically vertical cables, comprising 31 strands each, support the deck with a clear span of 170 metres. A total of 25 tonnes of strand has been used for the stays; the longest cable is 27 metres. Stay cables are protected at the deck end by galvanised steel anti-vandalism tubes.

The extremity anchorages are fixed at the upper end (into the arch) and adjustable at the bottom end, to allow the stays load regulation anytime.

The stay cables have been installed by a Tensacciai team at the erection yard alongside the channel, before the bridge load out and placing to its final position, utilising a winch system for threading the strands.

The strands have been installed by isoelongation at zero tensioning according to the design criteria; the final tensioning stage has been reached thanks to the dead load of the bridge itself; the strands have been prepared with reference to a witness strand of pre-fixed lengths.

click to enlarge


 
Project : DINTELHAVEN CABLE-STAYED BRIDGE
Location : Rotterdam (NL)
Type : Arch cable-stayed bridge
Total length of the bridge
: 270 m.
Main span
: 170 m.
Deck width : 10.8 m.
Deck type : Steel
Arch height : 42.5 m. over the deck
Stay cables : 25 tons
No. of stays : 30
Longest stay cable : 27 m.
Max. no. of strands per anchorage : 31 - 15.7 mm. dia.
Main Client : NS RAILINFRA-BEHEER-MANAGEMENT GROEP BETUWE-ROUTE (NL)
Contractor : HOLLANDIA BV (NL)
Designer : HOLLAND RAILCONSULT (The Netherlands)
Period : 12/1997 - 07/1998