Stay cables reference list

Page 1 of 3  > >>

High speed train line Milan – Bologna

18 12 2006
The new railway linking Bologna to Milan is part of the High Speed Lines network at present under construction in Italy.
[...]


The "Colletta" cable stayed bridge over the Sangone creek

16 07 2005
During the October 2000 flood almost all the watercourses in the province of Turin that were tributaries of the Po river underwent exceptional high waters and consequent flooding, which caused enormous economic and environmental damage.
[...]


Arch bridge over the Twente canal

06 07 2005
The existing double railway bridge was too low and too old. The crossing with the Twente canal was too low; the bridge was technically at the end of its lifetime. A unique opportunity to design and build another railway cable-stayed bridge in the Netherlands.
[...]


Cable-stayed bridge over the River Paranaíba

04 11 2003
Although the Paranaíba Bridge was the first cable-stayed bridge to break ground in Brazil
[...]


Sea Pallini bridge, Athens

02 10 2003
The “Sea Pallini” cable stayed bridge, crossing the main highway reaching the new airport of Athens...
[...]


Shaikh Khalifa Bin Salman arch bridge in Hidd, Bahrain

published: 26 05 2003
The unique project of the Shaikh Khalifa Bin Salman Arch bridge was started in April 2002

when fatigue and efficiency tests were carried out on 2 stay cables specimens in real scale assembled in the testing machines of the EMPA laboratories in Zurich (Switzerland) under the surveillance of the designer, Hyder Consultants UK.
This validating testing program led to brilliant results, with a positive fatigue behaviour and efficiency tests with excellent results, overcoming the 95% Fpk (nominal breaking load).

The steel structure of the Arch bridge was preliminary assembled by Cleveland Bridge Middle East in July – August 2002 in a dedicated area of the harbor of Dubai, U.A.E., where all steel parts were put together.
108 no. Tensacciai stays were here installed in the structure, 54 made of 16 strands and 54 made of 3, without tensioning and secured for sea transport.

In fact, in October, the bridge was moved onto a barge and transported to the final location of Hidd, Bahrain.
Here, after placing the structure over final abutments, stays were finally stressed.
Then a concrete deck was cast, giving permanent load to stays and structure: at this stage the installation program foresaw a regulation of stays’ load, which was carried out using dedicated Tensacciai adjusting jacks.

Installation of stays was completed with final wax injections in April 2003, few weeks after the starting of the war in Iraq.

Further details of the project can be found on the website of the General Contractor:
http://www.cbeme.ae/marinebridgebahrain.htm.

click to enlarge



Project : SHAIKH KHALIFA BIN SALMAN ARCH BRIDGE (SKBS)
Location : Hidd (Bahrain)
Main span
: 121 m.
Stay cables : 28 tons
No. of stays : 108
Max. no. of strands per anchorage : 16 - 15,7 mm. dia
Deck type : Steel-concrete
Main Client : STATE OF BAHRAIN - MINISTRY OF WORKS AND AGRICULTURE - ROADS DIRECTORATE (Bahrain)
Contractor : CLEVELAND BRIDGE U.K. (U.K.)
Designer : HYDER CONSULTING (U.K.)
Period : 08/2002 - 04/2003