Preliminary monitoring and maintenance activities for the structural rehabilitation of "dell’Indiano" bridge

18 01 2005
Within the general works for the extra-ordinary maintenance and structural rehabilitation of the "dell’Indiano" bridge...
[...]


Rehabilitation of the 26th floor of Pirelli skyscraper

18 12 2003
On the 22nd April 2002 a small airplane crashed into the Pirelli skyscraper in Milan, causing the death of 2 persons and huge damages to the higher floors of the building.
[...]


Rehabilitation of Kwanza cable stayed bridge

15 10 2002
The original cable stayed bridge was built between 1970 and 1975.
It was made using as stay cables wire ropes crossing over saddles on the pylon.
[...]


Rehabilitation

Preliminary monitoring and maintenance activities for the structural rehabilitation of "dell’Indiano" bridge


published: 18 01 2005
Within the general works for the extra-ordinary maintenance and structural rehabilitation of the "dell’Indiano" bridge, works awarded to the Italian Contractor Impresa Geom. Santalucia Antonio by the Municipality of Florence, Tensacciai has carried out all the preliminary activities related to the monitoring of cable stays.

The Contract has foreseen a preliminary campaign to analyse the corrosion status of the single wires constituting the old stay cables and the determination of the acting forces inside each stay.
Further to this step, it has been carried out the total substitution of the outside protection of the stay cables.

Working activities have been the following:
- removal of the outside polyethylene ducts
- removal of the inner cement grout
- wires protection treatment through the use of preliminary sanding process and passivation with use of epoxy products
- installation of new high density polyethylene ducts, comprising telescopic tubes and anti-vandalism tubes

Further to these activities, since during preliminary test campaign it has been noticed an abnormal tensional status in one of the back stays, one full stay cable has been completely removed and substituted with a Tensacciai 81TSRA15 stay cable made of 81 strands type 15,7 mm diameter.

click to enlarge



Project : Preliminary monitoring and maintenance activities for the structural rehabilitation of "dell’Indiano" bridge
Location : Florence, Italy
Type : Rehabilitation of stay cables protection and total substitution of one stay cable
Stay cable total length : 1.245,00 m, average length of each stay 89 m
No. of stays : 14 stays made of wires diam. 7 mm
Main Client : Municipality of Florence
Contractor : Impresa Geometra Santalucia Antonio
Designer : Prof. Eng. Salvatore Giacomo Morano
Period : 2003-2004